On-site testing – metal facade fixing in a fire-resistant application
In one of the projects, the design called for insulation to be installed in fire barrier zones with a required fire resistance of R120. Rawlplug R-MBA anchors passed the test with no issues – both on paper and in practice.
On-site testing – metal facade fixing in a fire-resistant application
In one of the projects, the design called for insulation to be installed in fire barrier zones with a required fire resistance of R120. Rawlplug R-MBA anchors passed the test with no issues – both on paper and in practice.
On-site testing – roof screws and membrane fastening in OSB board
At one of the construction sites, the contractor faced a task that required exceptional precision – fastening the roofing membrane directly to the OSB board layer. The Rawlplug team carried out a series of tests to identify the optimal solution.
On-site testing – roof screws and membrane fastening in OSB board
At one of the construction sites, the contractor faced a task that required exceptional precision – fastening the roofing membrane directly to the OSB board layer. The Rawlplug team carried out a series of tests to identify the optimal solution.
Rawlplug at the heart of the industry – Fastener Fair Global and F&F Magazine
Fastener Fair Global in Stuttgart is more than just the world’s largest trade fair for fixings – it’s where the global industry meets, and where innovation goes hand in hand with experience. That’s exactly where Rawlplug – a brand operating since 1919 – confirms its position as a market leader.
Rawlplug at the heart of the industry – Fastener Fair Global and F&F Magazine
Fastener Fair Global in Stuttgart is more than just the world’s largest trade fair for fixings – it’s where the global industry meets, and where innovation goes hand in hand with experience. That’s exactly where Rawlplug – a brand operating since 1919 – confirms its position as a market leader.
New pages for designers – software and services always at hand
Check what you can gain from the new features. A personalised homepage and new subpages fully dedicated to the EasyFix and BIM programmes – this is just the beginning of the changes we’ve prepared on the eRawlplug platform with designers, engineers and architects in mind.
New pages for designers – software and services always at hand
Check what you can gain from the new features. A personalised homepage and new subpages fully dedicated to the EasyFix and BIM programmes – this is just the beginning of the changes we’ve prepared on the eRawlplug platform with designers, engineers and architects in mind.
Order processing downtime: 1st – 6th April 2025
From 1st to 6th April, we are implementing a new ERP system that will improve order processing through automation. During this period, there will be a temporary pause in order fulfilment.
Order processing downtime: 1st – 6th April 2025
From 1st to 6th April, we are implementing a new ERP system that will improve order processing through automation. During this period, there will be a temporary pause in order fulfilment.
Rawlplug products used in the modernization of the Kielce railway station!
After more than half a century of operation, the railway station required comprehensive modernization to meet contemporary standards. In 2021, a decision was made to renovate the facility, making it part of one of the most ambitious investments within the Railway Investment Program for 2016–2023.
Rawlplug products used in the modernization of the Kielce railway station!
After more than half a century of operation, the railway station required comprehensive modernization to meet contemporary standards. In 2021, a decision was made to renovate the facility, making it part of one of the most ambitious investments within the Railway Investment Program for 2016–2023.